How to install a Single Girder Overhead Crane? 5 ton single girder overhead crane installation procedures for reference. Overhead crane installation. It is critical to make the overhead crane installation process safe and orderly, which must be planned, organized, and built step-by-step in order to assure smoothness of single girder overhead crane installation. Each job employee must be aware of the following construction plan and be able to apply it with ease:
1. Site selections for installation
The site space of a single girder overhead crane installation should be sufficient to fulfill the needs of an overturn lifting installation, as well as the ability to plug in welding machines and other electric tools.
2. Equipment and tool preparation
Two sets of welding machines, two sets of oxygen acetylene, two sets of manual chain hoists, a cushion wooden ladder, lifting equipment, and a truck crane are required for the project.
3. Material preparation
This project requires a single girder overhead crane crane rail, platen, clamp, steel material for producing a single girder overhead crane baffle, slide wire, and welding rod, all of which must be prepared in advance.
4. Working staff involved.
Determine how many people will be involved in this project: One electrician, one fitter, one riveter, one welder, one lifting worker, and one safety/head.
5. Basic safety requirements
Construction staff must closely adhere to the standards of safe operation of each type of construction activity in order to participate in this project; illegal operations are prohibited.